2026 · Commercial PEMB
Commercial metal building cost per square foot
Supply and erect ranges from our own recent commercial bids for general contractors across the Southeast, and what moves the number.
About $20 – $45 per sq ft
supply + erect, from our 2026 bids: the low end is a large open-wall, roof-only building, the high end an enclosed, insulated building around 10,000 sq ft. Concrete, site work and interior are separate.
Ranges from our recent bids
| Building | Supply + erect |
|---|---|
| Open-wall warehouse or canopy (roof only), 50,000+ sq ft | about $20 to $25 per sq ft |
| Enclosed, insulated warehouse or shop, around 10,000 sq ft | about $38 to $45 per sq ft |
Steel building package plus erection, from our own 2026 bids. Concrete, site work, interior and MEP are separate. Every bid is priced from the plans and the manufacturer's quote, so your number will be its own.
What moves the price per square foot
- Walls and insulation: an open, roof-only building costs far less per foot than an enclosed, insulated one
- Size: bigger buildings spread equipment and setup over more square feet
- Eave height, crane needs and bay spacing
- Wind, snow and seismic loads where the building sits
- Doors, framed openings, canopies, liner panels and accessories
- Lift equipment and the schedule
What we do for general contractors
- Pre-engineered steel building package, supply and erect
- Takeoff from your plans and a 2-page proposal with scope, exclusions and clarifications
- 3D model of the building for your team and owner
- No bonds; projects of about 10,000 to 60,000 sq ft across the Southeast
Common questions
How much does a pre-engineered metal building cost per square foot?
From our 2026 bids, supply and erect: about $20 to $25 per sq ft for a large open-wall, roof-only building, and about $38 to $45 per sq ft for an enclosed, insulated building around 10,000 sq ft. Concrete, site work and interior are separate.
Does that include the foundation?
No. These ranges are the steel building package and erection. Foundations and slabs are priced separately.
Why is a smaller building more per square foot?
Equipment, setup and engineering cost about the same whether the building is 10,000 or 50,000 sq ft, so smaller buildings carry more of it per foot.
Where do you work?
Across the Southeast: Georgia, the Carolinas, Tennessee, Florida and Alabama.
How do I get a bid?
Send your plans and bid date, or call 800-952-5997. We price from the plans and the manufacturer's quote and send a 2-page proposal.



See your exact price now
Design it in 3D on Live Pricing and see your installed price in minutes. Change the size, doors, height and colors and the price updates as you go.